Please refer to our Privacy policy for important information on the use of cookies. By continuing to use this website, you agree to this.

Boston Haven Flood Defence Scheme

    Boston Haven Flood Defence Scheme

Boston Haven Flood Defence Scheme

Interserve helped the local community during the construction works.

Boston Haven Flood Defence SchemeThe existing steel sheet pile flood defence wall runs along the River Haven, Boston and dates from the 1930’s. As part of the Environment Agency’s progressive Flood Defence Scheme and Maintenance Works they determined the wall needed replacing. Interserve were contracted to install a new 240m long sheet piled wall in front of the existing. The new sheet piled wall design, as well as requiring the installation of new sheet piles, required anchors to be installed every 1.4 metres, extending 19 metres into the ground at a 30o angle. A new capping beam installation was of steel construction. Interserve used innovative techniques to reduce the risks of pouring concrete in an estuarine environment and to reduce the extent of site works.

New Flood Wall Installation

In 2013, Boston experienced the worst floods in its history. The existing apron was the issue and was undermined by scour and free flowing water over time, and there was also a grassed area between the existing sheet piles and the existing brick flood wall. The new one that we designed, procured and built in 6 months replaced all of this with a higher 1.5m high concrete wall in front of the existing brick wall, and replaced the grassed area with a structural concrete slabs Interserve secured the contract to re-construct the existing flood defence wall. As part of it formed the garden wall to a number of local properties, the new flood wall was constructed in front of the existing. It consisted of a reinforced concrete wall 1.5m high with a 3m apron. As this Apron did not fully cover the section to the existing capping beam , an additional fibre reinforced concrete slab was cast between the new apron and the existing capping beam thereby preventing water ingress which could scour and undermine the structure.

Value added initiatives

The knowledge gained from our previous experience on tidal river works and our in-house marine department was crucial in developing the solutions to the river side accesses. The project benefitted from the use of our own marine plant. Our own marine kit allowed us to work from the river to do the works, without the need to work on the bank, which was a narrow corridor. It also allowed us to use heavier plant and maintain better land side access along the 4 meter wide easement. The result was a safer, quicker and better value project.

Engagement with the local community

  • Boston College: We had 6 work experience students from Boston College on site taking part in construction activities and another 60 students came to visit. There were also 12 lectures to see the works activities and 5 toolbox talks were carried out at Boston College for the students studying bricklaying, carpentry, plumbing and BTEC construction.
  • The main site was locatedwithin the port in Boston. All deliveries were taken to a wharf and delivered to site on the river using a crane barge. This meant deliveries did not impact on the public, with the reduction of risk to pedestrians and cyclists.
  • A public relation with toolbox talk was carried out with all operatives who carried around business cards to issue to any interested parties.
  • Helped the owners of a containerised cafe to evacuate their merchandise as required by the council.
  • We repaired footpaths damaged by the flood event and secured residents gardens from collapsing into the holes created by the flood water.
  • Assisted one local in gaining access to this house when his door became blocked by the movement of his furniture.
  • A nurse who worked nights, was given a room on several occasions at a hotel away from the works area at our expense so that her restorative sleep patterns could be maintained. A boat called 'Boy Ben' sank in the river Haven. Its owner admitted the vessel was a total loss and that it must be moved for the safety of navigation and to minimise any further pollution - which is an offence. We righted the vessel and sailed the boat to the port of Boston to be lifted out. We offered to scrap her, however two locals wanted her and so we donated it to them. Their intentions were to refurbish, rename and resail her.

"Was out on site this morning in Boston and I have to say the works are looking very good.

Interserve are finalising garden remedial works and all works should be completed by the end of this week.

I'm pleased to say that Darryl and the team on site have worked hard to ensure that the site will be handed over defect free.
Well done to all involved and thank you for all your hard work."

Email from our client The Environmental Agency

latest insight

Explore our Latest Insight for further blogs, videos and research.


Tilbury Docks Barrier Refurbishment

The Thames Estuary 2100 Strategy outlines the need to maintain a tidal defence across the entrance to Tilbury Docks until the year 2050.

Boston Haven Flood Defence Scheme - New Flood Wall Installation

In 2013, Boston experienced the worst floods in its history. Interserve were contracted to install a new 240m long sheet piled wall in front of the existing.

Truro Flood Defence Scheme

The Truro Tidal Defence Scheme involved replacement of a 296m length of the tidal quay with a sheet pile wall supported by ground anchors, and a cathodic protection sy...

Get in touchWant to know more? send us a note here and we'll be in touch

Interserve is committed to protecting and safeguarding your personal data. Please visit our Privacy Policy to find out how your data is used.

*denotes mandatory field

There was an error submitting the form. Please try again.

Thank you. Your message will be with us shortly.
If you wish to write us another message please go back.
We will be in touch soon.

Share your thoughtsShare your thoughts

Please leave a comment below.

comments powered by Disqus